Tenant fit-outs inside a managed building
A Gurgaon office installation usually happens inside a building the client does not own, and that dictates the project more than any technical factor. Work must fit the building management's approved contractor process and fit-out hours, which are often evenings and weekends. The tenant's access control has to interface sensibly with the base-build system so the landlord's turnstiles and the tenant's floor doors are not two unrelated credentials. Most importantly, the base-build fire alarm already exists and any access-controlled door the tenant adds on an escape route must be interlocked to it - this is the single most frequently missed requirement in fit-out projects.